Concept Architecture
Concept
Theoretically, Time-Driven Activity-Based Costing (TDABC) is a resource costing methodology that estimates the cost of supplying healthcare services by assigning resource costs according to the time required to perform each activity. It extends traditional activity-based costing by replacing multiple cost drivers with time equations and capacity cost rates, providing a simpler and more accurate representation of resource consumption. In health economics, TDABC is widely used to estimate patient-level costs, clinical pathway costs and healthcare process costs.
Mathematically, Time-Driven Activity-Based Costing is based on two parameters: the capacity cost rate of a resource and the time required to perform each activity. Total activity cost is calculated by multiplying the time consumed by the cost per unit of practical capacity. Time equations may be used to account for variations in patient complexity or service delivery.
In practice, TDABC is implemented by mapping clinical pathways, estimating the practical capacity of personnel and equipment, calculating capacity cost rates and measuring the time required for each process. The resulting patient-level cost estimates are used in economic evaluations, value-based healthcare, process improvement and resource allocation.
Purpose
Used to estimate the cost of healthcare services by measuring the time required for clinical activities and assigning resource costs according to practical capacity utilisation.
Mathematical Formulae
Primary Formula
Activity Cost = Capacity Cost Rate ? Time Required
where:
- Capacity Cost Rate = cost per unit of practical capacity (for example, � per minute)
- Time Required = time consumed by the activity
Supporting Formulae
Capacity Cost Rate:
Capacity Cost Rate = Total Resource Cost / Practical Capacity
Time equation:
T = ?? + ??X? + ??X? + ? + ??X?
where:
- T = estimated activity time
- X? = activity characteristics affecting processing time
- ?? = estimated time parameters
Related Mathematical Methods
- Activity-Based Costing
- Micro-Costing
- Process Mapping
- Cost Allocation
- Capacity Cost Analysis
Example
A specialist nurse costs �96,000 annually and provides 96,000 minutes of practical clinical capacity each year.
Capacity cost rate:
96,000 / 96,000 = �1.00 per minute
A patient consultation requires 35 minutes.
Activity Cost = 1.00 ? 35 = �35
The consultation cost assigned using TDABC is �35.
Excel Implementation
| Function | Example Formula | Health Economics Application |
|---|---|---|
| Division | =B2/C2 | Calculates the capacity cost rate from annual resource cost and practical capacity |
| Multiplication | =D2*E2 | Calculates activity cost from time required and capacity cost rate |
| SUM | =SUM(F2:F25) | Calculates the total cost of a patient's care pathway |
| SUMPRODUCT | =SUMPRODUCT(D2:D25,E2:E25) | Calculates total costs across multiple clinical activities |
VBA (Optional)
Automate patient-level TDABC calculations by importing process times, applying capacity cost rates and generating pathway costing reports.
Sources
- Kaplan RS, Anderson SR. Time-Driven Activity-Based Costing. Harvard Business Review. 2004.
- Kaplan RS, Porter ME. How to solve the cost crisis in health care. Harvard Business Review. 2011.
- Kaplan RS, Witkowski M, Abbott M, et al. Using Time-Driven Activity-Based Costing to identify value improvement opportunities in healthcare. Journal of Healthcare Management.
- Drummond MF, Sculpher MJ, Claxton K, Stoddart GL, Torrance GW. Methods for the Economic Evaluation of Health Care Programmes. Oxford University Press.
- Briggs A, Claxton K, Sculpher M. Decision Modelling for Health Economic Evaluation. Oxford University Press.
Related Concepts (2)
Frequently Asked Questions (6)
What is time-driven activity-based costing?
A simplified variant of activity-based costing using the cost per unit of time for resource capacity and the time an activity takes, rather than activity surveys.
Source: Kaplan & Anderson 2004
How does time-driven activity-based costing work?
Two estimates are required rather than a full activity survey. The first is the cost of supplying capacity for a unit of time, obtained by dividing the cost of a resource by the time it is practically available, which is normally less than the theoretical maximum. The second is the time each activity actually takes. Multiplying the two gives the cost of the activity, and summing across activities gives the cost of an episode. Costs then follow time consumed rather than being apportioned by survey. Practical capacity is normally estimated at a proportion of theoretical availability, allowing for breaks, training and administrative time, and that proportion should be stated since it scales every cost the model produces.
Source: Kaplan & Anderson 2004
Why was time-driven activity-based costing developed?
Because conventional activity-based costing proved too burdensome to maintain. It required staff to be surveyed periodically about how their time divided between activities, and the resulting models became large, expensive to update and prone to drifting out of date as practice changed. Replacing the survey with two directly estimable quantities reduced the maintenance requirement substantially while retaining the principle that costs should follow what actually consumes them. The method also updates more readily, since a change in practice requires only the affected time estimates to be revised rather than the whole activity structure to be resurveyed.
Source: Kaplan & Anderson 2004
What does time-driven activity-based costing reveal that other methods do not?
Unused capacity, which appears explicitly as the difference between the cost of capacity supplied and the cost of capacity consumed, rather than being buried in the cost of the work performed. Conventional absorption spreads the whole cost across whatever activity occurred, so a lightly used facility shows a high unit cost and gives no indication that the problem is utilisation rather than efficiency. Separating the two directs attention to the right question. This makes the method useful for capacity planning as well as costing, since the unused portion indicates how much additional activity could be absorbed before further investment is required.
Source: Kaplan & Porter 2011
Where is time-driven activity-based costing used in health services?
In patient-level costing, where timestamps from theatre, imaging and pathology systems supply the durations the method needs without additional collection. It underpins work costing complete care pathways, where the objective is to establish what treating a condition actually consumes from first presentation to resolution. It is also used to compare the cost of delivering the same procedure in different settings, since it isolates time and rate rather than reporting a combined average. It also supports comparison between providers, since differences in time consumed and differences in the cost of capacity can be reported separately rather than combined into a single average.
Source: Kaplan & Porter 2011
What are the limitations of time-driven activity-based costing?
Time is a good proxy for resource consumption where staff and equipment dominate and a poor one where consumables or drugs do, since those vary with the case rather than its duration. Estimating practical capacity requires a judgement about what proportion of available time is genuinely productive. And activities differing in intensity rather than duration are misdescribed, since two hours of routine work and two hours of complex work receive the same cost. Time estimates themselves are frequently obtained by observation of a small number of cases, so the precision of the resulting figures should not be overstated.
Source: Kaplan & Anderson 2004
Trust Record
Verified by Dr Darrin Baines
British health economist
Professional identity: darrinbaines.org
Verification date: 8 Aug 2025
Content version: 1.0.0
Canonical Identity
- Persistent URI
- https://healtheconomics.wiki/concept/time-driven-abc
- Term code
- HE-EE-CM-017
Stable URI · Machine-readable · Resolvable · CC BY 4.0